HRERA directs refund with interest after project registration lapse

A Haryana RERA order directed refund of a buyer’s ₹14.51 lakh payment with 10.80% annual interest after the affordable-housing project failed to progress and its registration lapsed.

GurugramDevelopment: 7 September 2026Published: 8 September 2026

The dispute concerned an affordable home in Gurugram

The reported Haryana RERA order arose after a buyer paid approximately ₹14.51 lakh toward an affordable-housing unit and found that the project had not progressed as promised. The authority’s decision must be read against the exact project, allotment, payment trail and registration record; it is not a blanket refund order for unrelated projects.

Why the registration position mattered

A project registration has a stated validity period and may later be extended, completed, revoked or allowed to lapse. A lapsed status does not by itself decide every buyer’s remedy, but it is a serious signal to open the precise registration record, quarterly progress, extension orders and any completion or occupancy documents before making or continuing payments.

The reported financial direction

The report states that the authority ordered refund of the buyer’s deposited amount with 10.80% annual interest. The amount recoverable in any other case will depend on its own payment dates, agreement terms, relief sought and operative order. Buyers should obtain the signed order rather than relying only on a headline summary.

What a buyer should preserve

Keep the application, allotment letter, agreement for sale, bank statements, receipts, demand notices, promised possession date and all project correspondence. Download the RERA registration certificate and later orders while they are available, and match the unit, tower or plotted phase to the same registration number.

Checks before paying into a delayed project

Search the exact phase on the Haryana RERA portal, compare the validity and declared completion dates, open quarterly progress reports and verify the on-ground construction position. If a refund, possession or interest claim is being considered, obtain transaction-specific legal advice before signing a settlement or cancellation document.

Source documents and reports

Economic Times report — 7 September 2026Haryana RERA official portalHaryana RERA Gurugram registered-project searchReal Estate (Regulation and Development) Act, 2016

Considering property in Gurugram?

Send the project name, budget and intended use for current market information.